Quick webcast today on overallocation, and looking at the calendar and fine level time phasing to see why Project thinks the way it does.

Shortly after recording this I also discovered that if you have actual work equal to the planned work in the scenario described then it does not show in red as overallocated. I guess if you managed to work 2 hours in 1 hour then not worth re-planning :).